Jan 19, 2015
Delay in its projects leading to a steep escalation in cost has proved to be the bane of the DRDO. The delays have led to the country being left with no option but to equip the armed forces with expensive foreign equipment.
A report of the Parliamentary Standing Committee on defence tabled in Parliament just last month let the cat out of the bag.
“The committee notes that there are about 530 ongoing projects in different DRDO labs and out of them 136 are in mission mode. Some of these include Agni IV, Agni V, Nirbhay cruise missile, K-15, Nag, Astra, AWACS, Arjun main battle tank, Tejas light combat aircraft, etc. The committee also note that out of 44 major ongoing projects (more than Rs 100 crore), there have been cost revisions and time revision in case of eight and 12 projects respectively. Besides, 10 projects are more than five years old i.e. sanctioned before 2009. Eighteen major projects (more than Rs 50 crore) were sanctioned during the 10th Five Year Plan (April 2002 to March 2007) but none has yet been completed. Two of them have been closed, five are awaiting closure and one under evaluation.
Out of 43 major projects (more than Rs 50 crore) initiated during the 11th Five Year Plan (2007-12) none has reached completion.”“The committee notes that many projects including development of cargo ammunition, development of GPS based system as an alternative to fire direction radar, development of 30 mm fair weather towed AD gun system, development of 30 mm light towed AD gun system have been closed thus wasting a considerable amount of public money.”
A few years ago, the then Parliamentary Standing Committee had observed, “The committee is of the view that the delays in development of weapon systems, MBT Arjun, LCA II, Integrated Guide Missile Development Programme i.e. Prithvi, Akash, Trishul, Nag and Agni, Kaveri engine for the LCA etc., not only has caused significant loss of revenue but also delayed the timely procurement of weapon systems from foreign sources that were needed to keep the forces fighting fit and modernised.”
The Arjun was one of DRDO’s main “indigenous” projects, cleared by the government over four decades ago, in 1974. But the inordinate delay in its execution meant that the cost escalated from about `15 crore in 1974 to `306 crore a decade ago, drawing severe criticism for the DRDO.
The Army too was unhappy with the tanks during trials, citing several flaws such as “failure of power packs, low accuracy and consistency, failure of hydropneumatic suspension units, shearing of top rollers and chipping of gun barrels. But in the past few years, the DRDO has made several improvements and modifications that has resulted in the Army accepting 124 Arjun MBTs. The DRDO is also developing the more improved Mark-II version of the tank.